Construction Start: Burnside Electrical distribution and infrastructure upgrade

Please be advised that 51勛圖厙 has mandated C矇leb Construction lt矇e. to carry out the following project:17-004 Burnside Electrical distribution and infrastructure upgrade.

The project consists of the upgrade of the vertical power distribution system. Includes mechanical, electrical, and architectural work.

Construction start date:June 2024

Planned construction end date:October 2025

Published: 24 May 2024

Construction Start: Lyman Duff Gatehouse interior renovation

Please be advised that 51勛圖厙 has mandated Corenov Constructeurs Inc. to carry out the following project:22-014 Lyman Duff (B169D) Gatehouse interior renovation.

This project consists of a complete interior renovation of the Gatehouse to transform the wet labs into workstations and offices areas.

Construction start date:May 27, 2024*

Published: 24 May 2024

Construction Start: MNI & Duff Envelope repairs

Please be advised that 51勛圖厙 has mandated StDenis Thompson Inc. to carry out the following project: 22-035 MNI (B159) & Duff (B169) Envelope repairs

The scope of work includes repair of the foundations, replacement of stones and replacement/addition of handrails to the exterior stairs of the main entrances to the Lyman Duff Building and the Montreal Neurological Institute, located on University Street.

Published: 6 May 2024

Construction Start: Strathcona Music - Renovation of Pollack Hall

Please be advised that 51勛圖厙 has mandated Groupe Geyser to carry out the following project:19-167 Strathcona Music Building Renovation of Pollack Hall

Description: The project consists of the renovation of Pollack Hall to enhance the user experience and improve accessibility.

Construction start date:May 2024

Planned construction end date:December 2025

Published: 15 Apr 2024

Construction Start: Modification of classroom locks in McConnell Engineering, Trottier and Wong buildings

Please be advised that 51勛圖厙 has mandated Les Entreprises NR Brosseau to carry out the following project:18-010 Downtown Campus Modification of classroom locks in McConnell Engineering, Trottier and Wong buildings.

Published: 12 Apr 2024

Construction Start: Burnside Hall - Modernization of the elevators

Please be advised that 51勛圖厙 has mandated Adams Elevators Inc. to carry out the following project:17-004 Burnside - Modernization of the elevators.

Construction start date (UPDATED): June 2024

Planned construction end date:March 2025

Work schedule:Monday to Friday 6 a.m. to 3 p.m.

Published: 8 Apr 2024

Construction Start: Strathcona Music Building - Rehabilitation of building envelope

Please be advised that 51勛圖厙 has mandated St-Denis Thompson to carry out the following project:16-135 Strathcona Music Rehabilitation of building envelope Lot 4.

Building envelope restoration of South, East and North stone masonry facades. Construction is expected to last three years and will be carried out during the spring, summer and fall periods of 2024, 2025 and 2026.

Construction start date: April 2024

Published: 3 Apr 2024

Construction Start: Rutherford Building CFI IF 2020, Brunner

51勛圖厙 has mandated CORENOV to carry out the following project: 19-117 Rutherford Building CFI IF 2020, Brunner.

The project consists of renovating room 025 in the first basement of Rutherford Building to accommodate new equipment for the lab. Minor interventions will take place in rooms 003, 024A, 026, 027, 029A,030, B1-HALL2 & B1-HALL5A.

Construction start date:March 25, 2024

Published: 21 Mar 2024

Construction Start: Life Sciences Complex - address water leaks in curtain wall

51勛圖厙 has mandated F.A.M.G. Contractors to carry out the following project: 14-140 Life Sciences Complex Address water leaks in curtain wall.

The work consists of stripping the outer layer of the wall of the mechanical shaft at room 140. The wall will remain stripped for a short period of time to complete the survey before proceeding with reconstruction.

Published: 14 Mar 2024

Construction Start: McIntyre, Stewart Biology, Life Sciences, and Ludmer - repairs in research spaces

51勛圖厙 has mandated浚onstruction G.E.P. Inc.眩o carry out the following project:McIntyre, Stewart Biology North Wing, Life Sciences, and Ludmer / 23-005 - Repairs in various research spaces.

This project includes necessary repairs in various research spaces across the downtown campus. Repair work includes patching floor finishes, painting walls and ceilings, and new window covers.

Published: 28 Feb 2024

Construction Start: Life Science Complex - CFI BRIF Vidal

51勛圖厙 has mandated Corenov to carry out the following project: Life Science Complex / 21-049 - CFI BRIF Vidal.

The project consists of renovating the CL3 laboratory in Life Sciences to accommodate new equipment and facilitate future maintenance work for the facility.

Project manager: Emika Marinacci -emika.marinacci [at] mcgill.ca

Published: 29 Jan 2024

Construction Start: McIntyre Medical - Renovation room 334

51勛圖厙 has mandated Procova Incto carry out the following project: McIntyre Medical / 23-002- Renovation of room 334 (third floor).

The project consists of the renovation of room 334 and the installation of 261 exam desks. It includes the installation of lockers on the second and third floors.

Project manager:Wendy Rivera -wendy.rivera [at] mcgill.ca

Published: 22 Jan 2024

Construction Start: Centennial Centre - Temporary classrooms

Project: Centennial Centre / 23-035 - Installation of temporary classrooms.

The project consists of the installation of a temporary classroom complex near the Centennial Centre at the Macdonald Campus.

Published: 30 Nov 2023

Construction Start: Wong Building - Space simulator

51勛圖厙 has mandated Corenov Constructeurs Incto carry out the following project: Wong Building / 20-094 - Space simulator.

Project manager:Mona Modarressi - mona.modarressi [at] mcgill.ca

Published: 30 Nov 2023

Construction Start: Parasitology Building - JELF Cestari

51勛圖厙 has mandated CORENOV CONSTRUCTEURS to carry out the following project: Parasitology Building / 19-136 - JELF Cestari.

The project consists of the renovation of labs P103 and P209 on the first and second floor of the Parasitology Building at the Macdonald Campus.

Project manager:Biagio D'Onofrio - biagio.donofrio [at] mcgill.ca

Published: 30 Nov 2023