Construction (Re)Starts: Reconstruction of Upper Main Road - Downtown Campus

Please be advised that, following a winter break, construction work will resume with Ceveco Inc. to carry out the following project:Â 19-016 Reconstruction of Upper Main Road, Downtown Campus.
¶Ù±ð²õ³¦°ù¾±±è³Ù¾±´Ç²Ô:ÌýReconstruction of the Upper Main Road, from the Y intersection to the McCall MacBain Arts Building, including underground work.
Construction restart date: March 31, 2025
Planned construction end date: November 2025
Work schedule:Â Monday to Friday, 6 a.m. to 7 p.m. /Â Saturday, 6 a.m. to 7 p.m.
Project Manager:Â simon.lacoste [at] mcgill.ca (Simon Lacoste)
Assistant Project Manager: marcela.fernandezpedrozo [at] mcgill.ca (Marcela Fernández Pedrozo)
--------------------------------------------------------------------------------------------------------
Scope of work:
- Demolition of existing road, from Y intersection up to front of McCall MacBain Arts Building.
- Excavation for installation of rainwater management system.
- Reconstruction of road, including underground work, paving, landscaping, and installation of new lighting and exterior furniture.
Impact & mitigation:
- Certain parts of Upper Main Road will be inaccessible to vehicular and pedestrian traffic at times. Alternative routes, including universal access, will be available and communicated through signage.
- There will be increased vehicle traffic from the Milton Gates to the mobilization site in front of the Macdonald-Harrington Building.
- Work will produce high levels of noise and dust.
- Some entrances to surrounding buildings will be closed at times. Users will be directed to alternative entrances.